最新的Oracle Manufacturing Cloud 2017 Implementation Essentials - 1z1-348免費考試真題

問題1
In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates of the assembly have been defined as required.
A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up costs, the extended costs of purchase components are not included in a rolled-up scenario.
Identify the reason.

正確答案: B
問題2
In a manufacturing plant, a production operator in a given shift completes a car assembly and reports this using orderless completion by referencing a Work Definition.
Identify the two purposes of the referenced Work Definition in Orderless reporting.

正確答案: A,C
問題3
The Plant Manager informs you that they have bought several machines for their manufacturing plant ABC. The plant has been set up with a separate cost element set ABC in Manufacturing Cloud. You are requested to configure these machines in such a way that those are costed to the work order for which operations are performed on these machines.
Identify the correct setup that you will advise to the Plant Manager.

正確答案: D
問題4
You can generate and manage work order exceptions in Oracle Manufacturing Cloud.
Which users can report production exception and who gets notified after an exception is raised?

正確答案: D
問題5
Your customer wants to mass create and modify Work Definitions and the relevant operation, items, and resources available in the spreadsheet.
Which two operations are not supported using ADFDI (Oracle Application Development Framework Desktop Integration)?

正確答案: B,D
問題6
A production operator needs to review the materials issued, resources charged, and operations performed for a job that was executed in the previous shift.
Identify the task the operator has to select to review all the transactions in a single place for both Work Order and Orderless execution.

正確答案: D
問題7
A Production Supervisor queries a Work Order (WO-1025) from the manage Work Orders page. On the Entering Edit Work Order: WO-1025 page, he finds General Information, Operations and History tab, but not the Reservations tab.
Identify the two reasons that can cause the Reservations tab not to be displayed.

正確答案: A,C