最新的SAP Certified Associate - Implementation Consultant - SAP S/4HANA Cloud Public Edition - C_S4CPB_2502免費考試真題

問題1
In which SAP Activate methodology phase do consultants configure business processes based on the information gathered in the Fit-to-Standard workshops?

正確答案: D
說明:(僅 VCESoft 成員可見)
問題2
After integration requirements have been finalized, what is used to analyze, design, and document the integration strategy?

正確答案: C
說明:(僅 VCESoft 成員可見)
問題3
If a customer wants to develop their own custom application and integrate it with SAP S/4HANA Cloud Public Edition, what tools would you recommend to develop the app? Note: There are 2 correct answers to this question.

正確答案: B,C
說明:(僅 VCESoft 成員可見)
問題4
Through which applications can you launch the Cloud Integration Automation Service (CIAS)? Note: There are 2 correct answers to this question.

正確答案: B,D
說明:(僅 VCESoft 成員可見)
問題5
You have assigned a deployment target in SAP Central Business Configuration, but have not yet completed the Confirm Scoping milestone.
Which of the following tasks can you complete? Note: There are 2 correct answers to this question.

正確答案: B,D
說明:(僅 VCESoft 成員可見)
問題6
What can you do with the SAP for Me mobile app? Note: There are 2 correct answers to this question.

正確答案: B,C
說明:(僅 VCESoft 成員可見)
問題7
In SAP Central Business Configuration, which activities can you perform in the Product-Specific Configuration Phase? Note: There are 3 correct answers to this question.

正確答案: A,B,D
說明:(僅 VCESoft 成員可見)