CMAA Construction-Manager 考試概覽:
| 認證廠商: | 美國建築管理協會(CMAA) |
| 考試名稱: | 認證建築管理師(CCM) |
| 考試代碼: | CCM |
| 及格分數: | 72%(150道計分試題中答對108題) |
| 考試時間: | 240 minutes |
| 證照有效期限: | 3年 |
| 考試形式: | 單選題 |
| 實際考試題數: | 175題(150道計分題+25道不計分試驗題) |
| 考試費用: | 575–750美元(依CMAA會員資格而定) |
| 相關認證: | CACM(初級認證建築管理師) |
| 支援語言: | 英文 |
| 範例考題: | CMAA Construction-Manager 範例考題 |
| 考試方式: | 於PSI考場採用電腦測驗(CBT)方式辦理;指定地點亦提供現場監考之紙筆測驗 |
| 必備條件: | 報考者須符合特定學歷與工作經歷要求:具備建築管理或相關領域學士學位,且擁有4年符合資格之相關經驗;或具備8年整體設計/營建經驗,並擁有48個月負責執行職務(RIC)之經歷 |
| 官方大綱網址: | https://www.cmaanet.org/certification/ccm |
CMAA Construction-Manager 考試大綱主題:
| 章節 | 權重 | 目標 |
|---|---|---|
| 合約行政 | 10% | - 索賠與爭議處理
|
| 計畫與專案管理 | 20% | - 專案規劃與協調
|
| 專業實務 | 10% | - 倫理與專業操守
|
| 永續發展 | 5% | - 能源效率
|
| 時程管理 | 10% | - 進度排程
|
| 安全管理 | 10% | - 事故管理
|
| 風險管理 | 10% | - 風險辨識與評估
|
| 科技應用 | 5% | - 資訊管理
|
| 成本管理 | 10% | - 預算擬定與管控
|
| 品質管理 | 10% | - 品質保證與品質管控
|
最新的 Certified Construction Manager Construction-Manager 免費考試真題:
1. A CM's responsibility for safety on the jobsite includes
A) drafting the contractor's safety plan.
B) certifying subcontractor compliance.
C) a professional obligation shared with others.
D) no obligation for safety as it is the contractor's responsibility.
2. A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am-7pm, 5 days per week and that the bridge would be completed by September 1.
The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.
The CM should
A) tell the contractor they have until September 1 and can only work 7am-7pm.
B) discuss with the owner and tell the contractor to do only 1/2 of the bridge.
C) meet with the owner and contractor to vet all issues/options and make a decision.
D) meet with the contractor to go over realistic time frames and make a decision.
3. An agency CM is overseeing the construction of a large, complex multi-story, high security building in a remote area. The building had a specialized spire installed at the top, which serves as an encrypted signal transmitter. Construction is complete and the contractor has de-mobilized, but then it is discovered that the signal transmitter is not transmitting the signal. The owner's QC plan required testing for the functionality of the transmitter, but the contractor has not shown test results reflecting adequate performance. Who is responsible for the cost of remobilization?
A) Owner
B) Contractor
C) Agency CM
D) Designer of record
4. Industry best practice is to conduct a pre-bid conference. The intent of the pre-bid conference is to
A) survey existing conditions and reveal unforeseen conditions.
B) limit the number of bidders on the project.
C) resolve any questions about contract requirements and scope of work.
D) mitigate change orders and delays.
5. Lifecycle analysis of a project will provide the greatest impact during which of the following phases?
A) Pre-Design
B) Procurement
C) Construction
D) Design
問題與答案:
| 問題 #1 答案: C | 問題 #2 答案: C | 問題 #3 答案: B | 問題 #4 答案: C | 問題 #5 答案: A |

下載最新試用版
979位客戶反饋
我們對我們的產品非常有信心,所以我們不提供会给客户带去麻煩的產品。








1.161.199.* -
上週,在CMAA 的 Construction-Manager 考試中我使用了你們提供的考試題庫,之后我通過了考試。你們的考題和答案是非常有幫助的。太幸運了,大多數考試中的問題都來自你們的題庫。