問題1
Skipped
An End-Of-Project Review may include the hiring of an external consultant to audit a project. This is particularly true in the Public Sector and for high-value/high-risk projects. The Auditor is likely to review the project's performance against what?
An End-Of-Project Review may include the hiring of an external consultant to audit a project. This is particularly true in the Public Sector and for high-value/high-risk projects. The Auditor is likely to review the project's performance against what?
正確答案: C
說明:(僅 VCESoft 成員可見)
問題2
Fred is comparing two possible projects that will last for different durations.
His company can only select one project due to financial constraints.
He needs a method to compare the financial benefits of both projects.
Q: Is a payback analysis a useful tool for Fred to use?
Answer Options:
His company can only select one project due to financial constraints.
He needs a method to compare the financial benefits of both projects.
Q: Is a payback analysis a useful tool for Fred to use?
Answer Options:
正確答案: C
說明:(僅 VCESoft 成員可見)
問題3
Why might a Public Sector Organisation use a PPP style of contract to build a new police station? Select ALL that apply.
正確答案: A,E
說明:(僅 VCESoft 成員可見)
問題4
When should a company use redundancy to implement change?
Answer Options:
Answer Options:
正確答案: B
說明:(僅 VCESoft 成員可見)
問題5
Under which style of contract is the client, rather than the construction company, responsible for the design of a building?
正確答案: A
說明:(僅 VCESoft 成員可見)
問題6
Salvador Ltd is a manufacturer of batteries for domestic appliances and hand tools. The company recently expanded due to excellent sales and introduced new machinery for producing solar-powered batteries.
They contracted Sunshine Ltd to build and install the machinery.
The contract specified that the machine must produce 5 batteries per hour, but currently, it is producing only 4 batteries per hour.
Salvador Ltd has agreed to work with Sunshine Ltd to resolve the issue within one month before liquidated damages apply.
Q: What stage is the project at?
Answer Options:
They contracted Sunshine Ltd to build and install the machinery.
The contract specified that the machine must produce 5 batteries per hour, but currently, it is producing only 4 batteries per hour.
Salvador Ltd has agreed to work with Sunshine Ltd to resolve the issue within one month before liquidated damages apply.
Q: What stage is the project at?
Answer Options:
正確答案: C
說明:(僅 VCESoft 成員可見)
問題7
Which of the following aspects of culture make up the 'paradigm of the working environment' according to Gerry Johnson and Kevan Scholes? Select all that apply
正確答案: A,B,C,D
說明:(僅 VCESoft 成員可見)
問題8
Cactus Construction is the Principal Contractor on a housing estate project under an NEC contract. Which of the following scenarios would be a mandatory variation?
正確答案: D
說明:(僅 VCESoft 成員可見)
問題9
When is the best time to define acceptance criteria for a project?
Answer Options:
Answer Options:
正確答案: A
說明:(僅 VCESoft 成員可見)