最新的Peoplecert MSP Practitioner, 5th edition - MSP-Practitioner免費考試真題

問題1
During the 'identify the programme' process, the SRO identified that the utility regulator may be considering a fair pricing policy to protect vulnerable customers. The introduction of this policy would have a significant impact on the benefits expected by UU. The programme manager included this information in the programme brief.
How well does this apply the 'deal with ambiguity' principle, and why?

正確答案: C
說明:(僅 VCESoft 成員可見)
問題2
As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?

正確答案: A
說明:(僅 VCESoft 成員可見)
問題3
Which document has the as-is state of organization?

正確答案: C
說明:(僅 VCESoft 成員可見)
問題4
There is a risk that the utilities market is changing, with green energy solutions becoming more attractive to customers. As UU does not currently offer this type of green energy, the benefits gained from cross-selling electricity and gas to current water customers may be overestimated.
Which activity is relevant in the 'plan' phase of the Plan-Do-Check-Act (PDCA) cycle?

正確答案: B
說明:(僅 VCESoft 成員可見)
問題5
Who produces Business Case?

正確答案: D
說明:(僅 VCESoft 成員可見)
問題6
UU has always used a linear project management methodology in the past with varying degrees of success.
During the 'design the outcomes' process, UU has decided to trial an agile approach to deliver projects throughout Tranche 1.
Which theme is being applied to the 'design the outcomes' process?

正確答案: D
說明:(僅 VCESoft 成員可見)