問題1
Company A is working on a project. The project's budget is EUR10,000.
The planned value as of date X is EUR4,000.
The project is 30% completed. 60% of the budget has been spent to date X.
The actual cost (AC) to date for the project is:
The planned value as of date X is EUR4,000.
The project is 30% completed. 60% of the budget has been spent to date X.
The actual cost (AC) to date for the project is:
正確答案: A
問題2
Bulk orders from the customer to Nokia are problematic for Nokia because:
正確答案: D
問題3
Which of the following inputs are part of the sales to delivery handover?
正確答案: D
問題4
At a given point in time, a project has CV = EUR700, CPI = 0.7, SV = EUR-1,300 and SPI = 1.3. the project is:
正確答案: B
問題5
For which of the following reasons can the cost baseline be updated?
正確答案: A
問題6
Which of the following data is not available in 4C?
正確答案: C
問題7
What transactions still can be done after the project financial closure?
正確答案: A
問題8
When should risk analysis be performed?
正確答案: D
問題9
What is the purpose of a Project Target Agreement (PTA)?
正確答案: D