問題1
Per NEC 690.11, what is the maximum allowable DC voltage for a PV system requiring arc-fault circuit protection?

正確答案: C
問題2
Most electric service providers require interactive PV equipment to comply with which for interconnection to their distribution grid?

正確答案: C
問題3
A technician has been called to a scale due to a low-performing array. The technician will perform tests in the
24-source circuit combiner box. After putting on the correct PPE and turning off and performing lock.tagout of the inverted and combiner disconnect. Which is the next step to safely begin electrical testing in the combiner box?

正確答案: B
問題4
A 15 kW array has a PR of 0.88 and 1600 kWh/m²/year insolation. What is the annual output?

正確答案: D
問題5
A module's power is 340W at STC. At 700 W/m² and 40°C with a coefficient of -0.38%/°C, what is the output?

正確答案: C
問題6
A 10 kW system has a total derate factor of 0.85 and operates at 5 PSH. What is the daily output in summer with 10% soiling loss?

正確答案: B
問題7
A PV system equipped with rapid shutdown requires a label stating ''RAPID SHUTDOWN SWITCH FOR SOLAR PV SYSTEM''.
Which is the BEST description of where this label is required?

正確答案: C
問題8
A grounding electrode is required at the location of all ground-mounted and pole-mounted PV arrays. Which type of grounding electrode is NOT permitted for arrays. Which type of the grounding electrode is NOT permitted for array grounding?

正確答案: C
問題9
While surveying a potential three-phase project, an installer measures the voltage at the point of utility interconnection. The results are as follows:
* Phase to phase: 240V
* Phase A neutral: 120V
* Phase B neutral: 208V
* Phase C neutral: 120V
Which is a likely cause of these reading?

正確答案: C
問題10
A rooftop PV array uses a ballasted racking system with a total weight of 4 psf. The roof's maximum allowable load is 20 psf, including a snow load of 15 psf. Is this installation permissible?

正確答案: B
問題11
A microinverter system uses 30 modules, each rated at 320W, with an inverter efficiency of 96%. The AC output is connected to a 208V three-phase service. What is the total three-phase power output?

正確答案: B
問題12
A PV system includes a 600V DC disconnect with a fault current rating of 10 kA. The available fault current from the inverter is 12 kA. What must be done to comply with NEC 110.10?

正確答案: C
問題13
A PV system's annual energy production is 15,000 kWh. After maintenance, production increases by 5%.
What is the new annual output?

正確答案: A
問題14
Which is a requirement for designated battery rooms?