問題1
An elementary school requires a renovation, selective demolition, and a major addition in order to accommodate a growing student population. An architectural firm has prepared schematic design plans incorporating the school's increased programmatic needs, including an enlarged library, cafeteria, and gymnasium; a secure courtyard; and additional space for administrative offices and classrooms. The main entrance was relocated in order to improve the traffic and pedestrian flow at the beginning and end of the school day, and additional parking was provided to comply with current zoning requirements.
The existing single-story masonry building was built in 1950. Two small additions were built later: the north addition will be kept and repurposed, but the south addition will be demolished. The building contains asbestos and lead in roof soffits, floor tiles, pipe insulation, and window paint. All existing mechanical systems need to be replaced; new systems have not been selected.
Considerations for the renovation include:
* The relocated front entrance must be easily recognizable, highly visible, and secure.
* Interior and exterior materials need to be durable and maintainable in order to withstand frequent student abuse, but also economical due to strict budget limitations.
* Good indoor air quality and increased energy efficiency are priorities for the selection of mechanical equipment.
After completion, the entire school should look uniform, without a distinctive difference between the existing building and new addition.
Building information:
* Construction Type is II-B.
The following resources are available for your reference:
* Existing Plans, including site and floor plans
* Proposed Plans, including site and floor plans
* Cost Analysis
* Zoning Ordinance Excerpts, for off-street parking requirements
* IBC Excerpts, showing relevant code sections
* ADA Standards Excerpts, showing relevant sections from the ADA Standards for Accessible Design Which of the following is the maximum height the platform can be above the gymnasium floor per the proposed design?
The existing single-story masonry building was built in 1950. Two small additions were built later: the north addition will be kept and repurposed, but the south addition will be demolished. The building contains asbestos and lead in roof soffits, floor tiles, pipe insulation, and window paint. All existing mechanical systems need to be replaced; new systems have not been selected.
Considerations for the renovation include:
* The relocated front entrance must be easily recognizable, highly visible, and secure.
* Interior and exterior materials need to be durable and maintainable in order to withstand frequent student abuse, but also economical due to strict budget limitations.
* Good indoor air quality and increased energy efficiency are priorities for the selection of mechanical equipment.
After completion, the entire school should look uniform, without a distinctive difference between the existing building and new addition.
Building information:
* Construction Type is II-B.
The following resources are available for your reference:
* Existing Plans, including site and floor plans
* Proposed Plans, including site and floor plans
* Cost Analysis
* Zoning Ordinance Excerpts, for off-street parking requirements
* IBC Excerpts, showing relevant code sections
* ADA Standards Excerpts, showing relevant sections from the ADA Standards for Accessible Design Which of the following is the maximum height the platform can be above the gymnasium floor per the proposed design?
正確答案: C
說明:(僅 VCESoft 成員可見)
問題2
An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces, administrative spaces and public/lobby spaces.
The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop.
The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway.
The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck.
Other considerations for the project include:
* Protected tree requirements are defined in the PD document.
* Easy pedestrian access must be provided from Sycamore Boulevard.
* All required parking for the clinic must be accommodated on site.
* Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF).
* Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes.
* All service equipment needs to be screened; see PD document for restrictions.
* Signage opportunities are important to the client.
* Acoustical privacy is a concern of the healthcare system.
The following resources are available for your reference:
* Drawings, including a perspective, plans, and exterior elevations
* Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion)
* Exterior Material Cost Comparisons
* Planned Development Document
* IBC Excerpts, showing relevant code sections
* ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design The client proposes massing changes to the current design as well as programming for future phases.
Which of the following scenarios is permitted?
The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop.
The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway.
The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck.
Other considerations for the project include:
* Protected tree requirements are defined in the PD document.
* Easy pedestrian access must be provided from Sycamore Boulevard.
* All required parking for the clinic must be accommodated on site.
* Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF).
* Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes.
* All service equipment needs to be screened; see PD document for restrictions.
* Signage opportunities are important to the client.
* Acoustical privacy is a concern of the healthcare system.
The following resources are available for your reference:
* Drawings, including a perspective, plans, and exterior elevations
* Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion)
* Exterior Material Cost Comparisons
* Planned Development Document
* IBC Excerpts, showing relevant code sections
* ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design The client proposes massing changes to the current design as well as programming for future phases.
Which of the following scenarios is permitted?
正確答案: B
說明:(僅 VCESoft 成員可見)
問題3
According to model codes, wind pressure can be positive on the roof of a low-rise building when wind is which one of the following?
正確答案: D
說明:(僅 VCESoft 成員可見)
問題4
An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces, administrative spaces and public/lobby spaces.
The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop.
The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway.
The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck.
Other considerations for the project include:
* Protected tree requirements are defined in the PD document.
* Easy pedestrian access must be provided from Sycamore Boulevard.
* All required parking for the clinic must be accommodated on site.
* Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF).
* Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes.
* All service equipment needs to be screened; see PD document for restrictions.
* Signage opportunities are important to the client.
* Acoustical privacy is a concern of the healthcare system.
The following resources are available for your reference:
* Drawings, including a perspective, plans, and exterior elevations
* Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion)
* Exterior Material Cost Comparisons
* Planned Development Document
* IBC Excerpts, showing relevant code sections
* ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design The architect and civil engineer are coordinating the design of the proposed pedestrian plaza fronting along Sycamore Boulevard and reviewing estimates for the cost of street trees. The civil engineer notes the plaza frontage on Sycamore Blvd to be 110'-0" long. Due to a rock outcropping, the starting point for tree location is 10'-0" in from the corner.
The landscape regulations of the planned development and the street tree cost estimates are as follows:
* 'Cathedral' Live Oak: $250 per tree
* Allee Elm: $200 per tree
* American Holly: $125 per tree
What is the minimum cost for street trees along the frontage described?
The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop.
The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway.
The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck.
Other considerations for the project include:
* Protected tree requirements are defined in the PD document.
* Easy pedestrian access must be provided from Sycamore Boulevard.
* All required parking for the clinic must be accommodated on site.
* Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF).
* Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes.
* All service equipment needs to be screened; see PD document for restrictions.
* Signage opportunities are important to the client.
* Acoustical privacy is a concern of the healthcare system.
The following resources are available for your reference:
* Drawings, including a perspective, plans, and exterior elevations
* Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion)
* Exterior Material Cost Comparisons
* Planned Development Document
* IBC Excerpts, showing relevant code sections
* ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design The architect and civil engineer are coordinating the design of the proposed pedestrian plaza fronting along Sycamore Boulevard and reviewing estimates for the cost of street trees. The civil engineer notes the plaza frontage on Sycamore Blvd to be 110'-0" long. Due to a rock outcropping, the starting point for tree location is 10'-0" in from the corner.
The landscape regulations of the planned development and the street tree cost estimates are as follows:
* 'Cathedral' Live Oak: $250 per tree
* Allee Elm: $200 per tree
* American Holly: $125 per tree
What is the minimum cost for street trees along the frontage described?
正確答案: A
說明:(僅 VCESoft 成員可見)
問題5
A proposed six-story commercial building will have a basement level with finished floor 20'-0" below grade.
The building site is located less than 1 mile from the coastline. A site survey indicates that the average site elevation is 5'-0" above sea level.
Based on the site-specific conditions, which four issues should the architect address in the design? Check the four that apply.
The building site is located less than 1 mile from the coastline. A site survey indicates that the average site elevation is 5'-0" above sea level.
Based on the site-specific conditions, which four issues should the architect address in the design? Check the four that apply.
正確答案: A,B,D,E
說明:(僅 VCESoft 成員可見)
問題6
The design of a large, one-story building to be used for the storage of confidential documents is being evaluated for security. The owners wish to have as much storage space as possible.
Which of the following design strategies would be the most economical solution to maximize security?
Which of the following design strategies would be the most economical solution to maximize security?
正確答案: B
說明:(僅 VCESoft 成員可見)
問題7
Structural costs for wind resistance increase exponentially as building height is increased, primarily due to which of the following factors? Check the two that apply.
正確答案: A,C
說明:(僅 VCESoft 成員可見)
問題8
A midrise concrete frame structure originally designed for an area of low seismic risk must be redesigned for use in an area of high seismic risk.
Which one of the following modifications will have the highest construction cost?
Which one of the following modifications will have the highest construction cost?
正確答案: A
說明:(僅 VCESoft 成員可見)