問題1
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)
正確答案: B
問題2
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
正確答案: A
問題3
Which three are project gate statuses? (Choose three.)
正確答案: B,C,D
問題4
Identify the valid approval group type applicable to Oracle Project Financial Management Cloud. (Choose the best answer.)
正確答案: B
問題5
Your organization has a requirement to retrieve the value of the cost center segment based on the department.
Which source can you use while defining the account rule to achieve this requirement?
Which source can you use while defining the account rule to achieve this requirement?
正確答案: A
問題6
Which three Cost Collection Flexfield core attributes can be derived during import if not explicitly entered in a transaction document?
(Choose three.)
(Choose three.)
正確答案: C,D,E
問題7
In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice. Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
正確答案: D