最新的Oracle Project Management Cloud 2021 Implementation Essentials - 1Z0-1057-21免費考試真題
問題1
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitmentfor $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
正確答案: A
問題2
In a Project Draft Invoice preview, quantity (hours) andunit price (bill rate) are shown as fields on the invoice.
Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantityof 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantityof 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
正確答案: B
問題3
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certainnumber of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)
What feature would you use to meet this requirement? (Choose the best answer.)
正確答案: B
問題4
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two
正確答案: D,E
說明:(僅 VCESoft 成員可見)
問題5
You configure one OTBI using Project Cross Subject Area AnalysisReal Time. You notice that all measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To-Customer and Contract and Contract Line dimensions. Identify the reason for this behavior. (Choose the best answer.)
正確答案: B
說明:(僅 VCESoft 成員可見)
問題6
Whichtwoattributes are available while enabling a task as a business object for social networking?
正確答案: C,D
問題7
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project:
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want todefine deliverables for your project requirementsthat are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want todefine deliverables for your project requirementsthat are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)
正確答案: A,D
說明:(僅 VCESoft 成員可見)
問題8
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)
正確答案: A,C
說明:(僅 VCESoft 成員可見)
問題9
Youare implementing Project Portfolio Management for a global professional services organization. In their Consulting Services line of business, it is common to use resources from different business units based on the skills required. Therefore, cross-chargetransactions happen between business units within the same legal entity.Transfer price calculations need to be based on raw costs, with no further adjustments to transfer price.
Identify two setups that can drive this borrowed and lent agreement. (Choosetwo.)
Identify two setups that can drive this borrowed and lent agreement. (Choosetwo.)
正確答案: B,D
說明:(僅 VCESoft 成員可見)
問題10
A project administrator is trying toassign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)
正確答案: D
說明:(僅 VCESoft 成員可見)