最新的Microsoft Managing Projects with Microsoft Project 2013 - 74-343免費考試真題

問題1
Your company uses Project Professional 2013.
You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task.
You need to set up a dependency between these two tasks.
What should you do?

正確答案: D
問題2
You manage a project by using Project Professional 2013.
A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.
You need to implement a solution to meet the stakeholder's request.
What should you do?

正確答案: B
問題3
You are a project manager who uses Project Professional 2013.
Your organization migrates all project plans from Microsoft Excel to Project Professional
2013. One of the directors of the company has several years of experience using Excel Pivot Tables to analyze and make decisions about projects.
You need to enable project managers to view relevant project information in Excel Pivot Tables.
What should you do?

正確答案: B
問題4
You are using Microsoft Project Professional 2013.
Three years ago, you successfully completed a project to review all of the suppliers within your organization, and you have been asked to run a similar project again. You still have the project plan from three years ago.
You need to use the most efficient method to produce a new plan with tasks based upon the old project plan.
What should you do?

正確答案: A
問題5
You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks.
You create two manually scheduled tasks and link them in a Finish to Start relationship.
The project team member asks you to increase the duration of the predecessor task.
You notice that the successor task start date is now before the finish date of the predecessor task.
You want the successor task to start after the predecessor finishes.
What should you do?

正確答案: C
問題6
You are a senior project manager, and your organization uses Project Standard 2013.
You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability.
You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours.
What should you do?

正確答案: C
問題7
You are a project manager who uses Project Professional 2013.
A customer has sent you a project plan, which contains several custom fields that you want to use in your project. You have a custom field named CF1 in the Number1 field in your project, and you have a custom field named CF2 in the Number1 field of your customer's project.
You need to copy the custom fields from your customer's project into your own. You do not want to overwrite your project custom field.
You open both projects.
What should you do next?

正確答案: D