問題1
You work for an organization that uses Project Server 2013. Single-entry mode is disabled.
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
During week one, a team member enters a total of 20 hours of actual work.
During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value
decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?

正確答案: D
說明:(僅 VCESoft 成員可見)
問題2
You are a project manager in an organization that uses Project Server 2013. You manage two projects named Proj1 and Proj2.
You create a deliverable dependency between both projects by taking the following actions:
- You create a deliverable named Deliverable1 against a milestone named Milestone1 in Proj1. The Finish date for Milestone1 and the Deliverable Finish date for Deliverable1 are the same.
- On Proj2, you associate a dependency that has a milestone named Milestone2 to the Deliverable1.
After several days of work, Proj1 has been rescheduled, which moves the Finish date for Milestone1 ahead by five days.
You need to ensure that these changes are reflected in both projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

正確答案: C,D
問題3
Your organization is using Project Online to facilitate the selection of optimal portfolios.
The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period of time by using the efficient frontier and the strategic value provided by the tool.
You need to ensure the tool provides the expected outcome.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

正確答案: A,C,F
說明:(僅 VCESoft 成員可見)
問題4
You are a team member for an organization that assigns your tasks on schedules. Single-entry mode is not enabled.
At the end of the week, you submit your timesheet in Project Server 2013. Default security settings are enabled. However, a task assigned to you should have been assigned to a coworker who does the same type of work and who has other tasks on the schedule.
The project manager who assigns the tasks is unavailable.
You need re-assign this task to your co-worker.
What should you do?

正確答案: B
問題5
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.
You notice that some projects have been published with incorrect data. You and the project managers spend a lot of time correcting the data problems.
You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:
-- --
Review the project data after the project managers create the projects.
Send the projects back to the project managers if you find incorrect data so that
they can make the appropriate corrections.
Repeat the data verification process unless the data does not have any errors.
Publish a project only when all of its data is correctly completed.
What should you do?

正確答案: B
問題6
You are a project manager in an organization that uses Project Server 2013. Project team members submit updates to tasks through Project Web App (PWA).
A project team member clicks Remove Task, and you approve it. You apply this change to the project.
The team member indicates that they only want to hide the task from that particular view, not remove the task permanently.
You need to ensure the task is returned to the Tasks page so it can be properly hidden.
What should you do?

正確答案: A
問題7
You are a project manager, and your organization uses Project Server 2013 with an enterprise resource pool.
After assigning resources, you discover that two of them are showing up as overallocated. These two resources also work on other projects that you cannot change.
You need to solve this problem.
What should you do?

正確答案: D
問題8
An organization has performed a portfolio analysis in Project Server 2013 by defining a list of drivers and establishing the prioritization for next year's portfolio.
You are finalizing the second quarter for the next year, which is when changes to the strategy will take place. For transparency reasons, the organization intends to keep historic analysis for a certain number of years.
You need to reevaluate your portfolio for the rest of the year, considering new projects and current executing projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

正確答案: A,B
問題9
You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

正確答案: D,E
問題10
Your work in a multinational corporation which uses Project Server 2013 to plan and control projects in different business units. Each business unit has its own portfolio of projects but can participate in strategic projects. The Project Management Office (PMO) has configured
Enterprise Project Types (EPTs) to create new products, launch marketing campaigns, and deploy new lines of business tools to comply with the governance processes.
One of your roles is to identify new products. A local team in Singapore produces an effective idea for a new product.
You need to create a business case for the next portfolio analysis. You need to gather general information about the new product by efficiently collaborating with the local team.
What should you do?

正確答案: C