最新的GAQM Associate in Project Management (APM) - APM-001免費考試真題

問題1
Which Process Group includes the Manage Stakeholder Engagement process?

正確答案: D
問題2
Success is measured by benefits realization for a:

正確答案: B
問題3
An output of the Create WBS process is:

正確答案: B
問題4
The component of the risk management plan that documents how risk activities will be recorded is called:

正確答案: B
問題5
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

正確答案: D
問題6
Which type of chart is a graphic representation of a process showing the relationships among process steps?

正確答案: A
問題7
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

正確答案: B
問題8
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

正確答案: C
問題9
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

正確答案: B
問題10
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

正確答案: C
問題11
In which Knowledge Area is the project charter developed?

正確答案: B