最新的SAP Certified Application Associate - Planning and GATP in SAP SCM APO 7.0 EHP1 - C-TSCM44-65免費考試真題
問題1
The customer wants to implement safety stocks dependent on forecast accuracy and replenishment lead time accuracy. Quantity-based complete deliveries are needed.
What do you have to do to achieve this?
Note: There are 2 correct answers to this question.
What do you have to do to achieve this?
Note: There are 2 correct answers to this question.
正確答案: B,E
問題2
Which of the following steps are necessary to generate an RFC connection that can be used for the APO Core Interface?
Note: There are 3 correct answers to this question.
Note: There are 3 correct answers to this question.
正確答案: A,D,E
問題3
Your customer creates an infinite multilevel MRP run for a finished product and its components using the process heuristic SAP_MRP_001.
Product heuristics are not maintained in the product masters and no strategy profile is selected in the planning run.
How are the strategy settings derived in this situation?
Product heuristics are not maintained in the product masters and no strategy profile is selected in the planning run.
How are the strategy settings derived in this situation?
正確答案: A
問題4
What is a feature of the SNP optimizer?
正確答案: D
問題5
The customer wants to use CTM to check for free stock in all locations first, and then for possible production.
How can you implement this scenario?
How can you implement this scenario?
正確答案: C
問題6
Which of the following configuration sequences describes the setup for "days' supply / receipt days" key figures within the product view correctly?
Note: The desired result is displayed in the screenshot.

Note: The desired result is displayed in the screenshot.

正確答案: B
問題7
There are 6 predefined SNP planning areas.
What is the common feature of all 6 planning areas?
What is the common feature of all 6 planning areas?
正確答案: A
問題8
Which of the steps described below do you need to perform when creating InfoObjects to set up a DP or SNP scenario?
正確答案: B

