最新的 Medical Professional Exams CCM 免費考試真題:
1. (In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)
A) Engineer
B) Employer
C) Contractor
2. Which two statements reflect an INCORRECT application of a Golden Principle?
A) The Contractor ' s right to suspend work (or reduce the rate of work) effective after giving not less than
3 months (in lieu of 21 days) notice to the Employer.
B) Deleting all the clauses in the General Conditions that refer to the DAAB/DAB.
C) When applying the FIDIC Red Book or Yellow Book, the Commencement Date shall be within 60 days after the Contractor receives the Letter of Acceptance, in lieu of 42 days.
D) Any deletions of General Conditions (GC) must be replaced with Particular Conditions (PC) that cover the same scope, and do not leave any roles, duties, obligations, rights, and risk allocation undefined.
3. (What is the maximum period for the Engineer to issue the Notice of Commencement Date?)
A) 84 days
B) 42 days
C) 14 days
D) 21 days
4. Which of the following situations form legally binding contracts? (2 correct answers apply) Choose all of the correct answers (multiple possibilities)
A) The Employer received the Contractor ' s Letter of Tender and issued Letter of Acceptance.
B) The Employer and the Contractor signed the Contract Agreement.
C) The Employer received the Contractor ' s Letter of Tender and issued a Letter of Intent.
D) The Employer received the Contractor ' s Letter of Tender and issued a conditional Letter of Acceptance.
5. (In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer's Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)
A) The Contractor should have foreseen such risks due to the region's history; therefore, Clause 19 is not applicable.
B) The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.
C) Violence is an Employer's Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.
D) This is an Employer's Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.
問題與答案:
| 問題 #1 答案: C | 問題 #2 答案: B,C | 問題 #3 答案: B | 問題 #4 答案: A,B | 問題 #5 答案: D |