問題1
What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

正確答案: B,D
問題2
What is the difference between coproducts byproducts?Note: There are 2 correct answers to this question.

正確答案: C,D
問題3
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

正確答案: A,C,D
問題4
Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.

正確答案: A,B,C
問題5
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.

正確答案: A,B
問題6
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.

正確答案: A,C
問題7
Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

正確答案: B,C
問題8
When does the system trigger replenishment for a Kanban container?

正確答案: A
問題9
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

正確答案: A,B