最新的SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 - C_TSCM42_66免費考試真題
問題1
In what sequence are the steps of material requirements planning performed in SAP ECC?
正確答案: D
問題2
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change therequirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.
Which of the following scenarios are applicable in this case?(Choose two)
Which of the following scenarios are applicable in this case?(Choose two)
正確答案: A,B
問題3
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
正確答案: A
問題4
Which of the following properties about the planning functions available in SAP ECC applies?
正確答案: C
問題5
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define?(Choose two)
What does a firming type define?(Choose two)
正確答案: B,D
問題6
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation.
What can be the origin of the formula parameters used for scheduling?(Choose three)
What can be the origin of the formula parameters used for scheduling?(Choose three)
正確答案: A,B,D
問題7
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements?(Choose three)
正確答案: C,D,E
問題8
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.
How is the resulting firming interval specified in this scenario?
How is the resulting firming interval specified in this scenario?
正確答案: B