An administrator needs to make sure an RF3 cluster can survive a failure of two complete racks without negatively affecting performance. The current cluster configuration consists of the following:
* 30 All Flash Nodes: distributed 10 nodes per rack across three 42U racks
* Each node is configured with 20TB usable storage all flash (Cluster Total 600TB Usable)
* Current cluster utilization is 500TB storage
* Storage containers have Erasure Coding enabled
Which configuration changes should be made to make sure the cluster meets the requirements?

正確答案: A
說明:(僅 VCESoft 成員可見)
問題2
An administrator is configuring an All Flash cluster to support the following workloads:
* Full clone virtual desktops
* Hadoop
* Write heavy databases
Which three correct configuration options should the administrator use to meet the item requirements?
(Choose three.)
For each procedure, indicate whether it is a correct or incorrect procedure that must be configured to meet the item requirements using the drop-down option.
正確答案:

Explanation

Ref:
問題3
An administrator manages the following two Nutanix AOS 5.15 cluster environment:
* Corp-cluster-01
* Corp-cluster-02
The VM images must be available only on Corp-cluster-01, but cannot be checked out to cluster Corp-cluster-02. The images also cannot be checked out to any other clusters that are registered with Prism Central in the future.
Which two configuration settings must the administrator choose when creating the image placement policy that satisfies the stated requirements? (Choose two.)

正確答案: C,D
說明:(僅 VCESoft 成員可見)
問題4
An organization is running a Nutanix Cluster based on AOS 5.10.x and VMware vSphere 6.7. Currently, the CVM network is segmented and Storage only nodes not present.
A new security project based on NSX is coming. VMware Distributed Virtual Switches are required. The administrator needs to prepare the environment for the new project.
Which step should the administrator use to initiate the project?

正確答案: B
問題5
An administrator receives reports about a Nutanix environment. The investigation finds the following;
* VMs are experiencing very high latency
* Each node is equipped with a single SSD, utilized at 95%
* Each node is equipped with three HDDs, utilized at 40%
Why are the guest VMs experiencing high latency?

正確答案: B
說明:(僅 VCESoft 成員可見)
問題6
An administrator receives an error indicating that the CVMs in the cluster are not syncing to any NTP servers. An investigation of the issue finds:
* The NTP servers are configured in Prism
* The time on all CVMs is the same
* Both the CVMs and AHV hosts are configured for the UTC time zone
Which two steps can be taken to troubleshoot this issue? (Choose two.)

正確答案: A,D
說明:(僅 VCESoft 成員可見)
問題7
An administrator needs to maximize storage potential in a six-node cluster. The container is configured with the following:
Post-process compression
Capacity deduplication
What should the administrator configure to increase space savings?

正確答案: C
問題8
An administrator is deploying a new application to a Nutanix Enterprise Cloud. The application requires a security to prevent unauthorized access. The application also uses many non-standard ports that are unique to it. Security should not be changed for existing applications.
What should the administrator do to meet these requirement?

正確答案: B
問題9
An administrator configure Active Directory (AD) authentication for their Nutanix environment. When login in using an AD user account, the login process takes more than one minute to complete. No delay occurs when logging a local account.
What should the administrator confirm to resolve this issue?

正確答案: D
問題10
A customer has a Nutanix cluster with 10Gb connectivity via switch fabric extenders. The administrator receives NCC health check errors of latency greater than 200ms.
Which action should the administrator take to resolve the NCC errors?

正確答案: B