最新的CompTIA Project+ Certification - PK0-005免費考試真題

問題1
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
* Purpose
* Scope of work
* Location of work
* Period of performance
* Deliverables schedule
* Applicable standards
* Acceptance criteria
* Special requirements
* Payment schedule
Which of the following documents did the client provide to the project manager?

正確答案: A
說明:(僅 VCESoft 成員可見)
問題2
A number of unexpected issues have occurred during the execution of a project that will negatively impact the timeline and costs. Which of the following would be best for the project manager to do to mitigate this situation?

正確答案: C
說明:(僅 VCESoft 成員可見)
問題3
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project's level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?

正確答案: D
說明:(僅 VCESoft 成員可見)
問題4
A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

正確答案: D
說明:(僅 VCESoft 成員可見)
問題5
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

正確答案: C
說明:(僅 VCESoft 成員可見)
問題6
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

正確答案: A
說明:(僅 VCESoft 成員可見)
問題7
Which of the following activities are performed during the closing phase? (Select three).

正確答案: A,B,G
說明:(僅 VCESoft 成員可見)
問題8
Which of the following is a quality assurance tool?

正確答案: A
說明:(僅 VCESoft 成員可見)
問題9
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost
$3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

正確答案: C
說明:(僅 VCESoft 成員可見)
問題10
A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

正確答案: D
說明:(僅 VCESoft 成員可見)
問題11
A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

正確答案: B
說明:(僅 VCESoft 成員可見)
問題12
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?

正確答案: D
說明:(僅 VCESoft 成員可見)
問題13
A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

正確答案: C
問題14
An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

正確答案: C
說明:(僅 VCESoft 成員可見)