問題1
Several team members report that meeting objectives are not being met.
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)

正確答案: C,D
問題2
Which of the following is the primary purpose of an MOA or an MOU?

正確答案: B
問題3
A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance? (Choose two.)

正確答案: B,E
問題4
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?

正確答案: D
問題5
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?

正確答案: A
問題6
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?

正確答案: C
問題7
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?

正確答案: B
問題8
A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference.
Which of the following is MOST likely to be the main challenge the influences this decision?

正確答案: A
問題9
A company hires an outside vendor to provide 24/7 support.
Which of the following documents would determine the contractual obligations?

正確答案: D
問題10
Which of the following project documents should be used to record the occurrence of an unplanned event?

正確答案: D