問題1
What product should be used to confirm the version number of ail products in a particular stage?
正確答案: B
問題2
Which project characteristic suggests that projects should have a defined start and a defined end?
正確答案: C
問題3
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.
正確答案: C
問題4
Which is a purpose of the Directing a Project process?
正確答案: B
問題5
Which describes a risk event?
正確答案: D
問題6
Which is a benefit of using PRINCE2?
正確答案: D
問題7
Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,
正確答案: D
問題8
Which is an objective of the Closing a Project process?
正確答案: B
問題9
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
正確答案: B
問題10
Who represents the three project interests on a project?
正確答案: B
問題11
Which is a purpose of quality planning?
正確答案: B
問題12
What theme estimates the cost of delivering the project?
正確答案: D
問題13
Which statement about risks is FALSE?
正確答案: C
問題14
If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?
正確答案: C