最新的PRINCE2 Foundation - PRINCE2免費考試真題
問題1
Which product provides the answer to the question, is the investment in this project still worthwhile?
正確答案: C
問題2
Which of the following would be carried out during the Starting Up a Project process?
正確答案: D
問題3
When it is forecast that one or more tolerances are to be exceeded, what should happen first?
正確答案: A
問題4
Which product produced by the Project Manager would contain information on 'products completed in the period'?
正確答案: B
問題5
Identify the missing word(s) in the following sentence... PRINCE2 recommends three [ ? ] to reflect the needs of the different levels of management involved in a project.
正確答案: C
問題6
According to PRINCE2, which of the following are the aspects of project performance to be managed?
正確答案: B
問題7
Which of the following shows the scope of a plan?
正確答案: C
問題8
What is the goal of the 'Identify context' step within the recommended risk management procedure?
正確答案: A
問題9
Who is responsible for providing the project mandate?
正確答案: D
問題10
Which PRINCE2 role has a specific responsibility for managing the information flows between the directing and delivering levels of the project?
正確答案: D
問題11
Which of the following is NOT one of the three levels of plan recommended by PRINCE2?
正確答案: B
問題12
Which process would review the performance of the project against its baselines?
正確答案: D
問題13
If a product's weight was specified to be 300 grams, but could only be built to a weight of 400 grams, which of the following would be created?
正確答案: C
問題14
Which of the following does PRINCE2 recognize as being project characteristics?
1.Projects are the means by which we introduce business change
2.Projects have a defined start and end
3.No project is unique
4.Projects often cross the normal functional divisions within an organization
1.Projects are the means by which we introduce business change
2.Projects have a defined start and end
3.No project is unique
4.Projects often cross the normal functional divisions within an organization
正確答案: D