問題1
Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product The stakeholder is unhappy with the slow performance, a complaint that the Product Owner agreeswithAs the Scrum Master how will you move this forward?
(choose the best answer)

正確答案: A
說明:(僅 VCESoft 成員可見)
問題2
True or False: During the Sprint Review of a scaled development effort, every Scrum Team should demonstrate its individual Increment separately.

正確答案: A
說明:(僅 VCESoft 成員可見)
問題3
What can the Scrum Value of openness easily impact?
(choose the best answer)

正確答案: B
說明:(僅 VCESoft 成員可見)
問題4
You are the Scrum Master for a Scrum Team whose Daily Scrum is scheduled to start at 10:00 each day.
Developers routinely turn up late, and once everyone has assembled, the Daily Scrum starts. By then it is typically 4 to 5 minutes later than scheduled. Other meetings in the organization typically allow 4 to 5 minutes for people to transport within the building.
Some Developers complain that it is now hard to achieve the purpose of the Daily Scrum within the timebox, since there is only 10 or 11 minutes left after waiting for people to show up. The Developers ask for your advice.
(choose the best answer)

正確答案: B
說明:(僅 VCESoft 成員可見)
問題5
A Scrum Team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do?
(choose the best answer)

正確答案: B
說明:(僅 VCESoft 成員可見)
問題6
In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient tor going to production In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions tor the Scrum Master to take?
(choose the best two answers)

正確答案: C,D
說明:(僅 VCESoft 成員可見)
問題7
Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?
(choose the best three answers)

正確答案: A,D,F
說明:(僅 VCESoft 成員可見)
問題8
You have just been hired as a Scrum Master by a company new to Scrum. The company wants to use Scrum to build a new product that was conceived by the product management department. You will be the Scrum Master of two new teams that will build a first version of the product. The product management department assigns two new Product Owners, but wants more advice about the required participationwith the new Scrum Teams. Which two suggestions would you offer?
(choose the best two answers)

正確答案: C,D
說明:(僅 VCESoft 成員可見)