問題1
Factors that are important to take into account when performing test estimation include:
i. The quality of the test basis
ii. The availability of test automation
iii. The amount of rework required
iv. The distribution of testing across several locations
The various factors can be grouped by characteristic. Examples of characteristics include:
i. The quality of the test basis
ii. The availability of test automation
iii. The amount of rework required
iv. The distribution of testing across several locations
The various factors can be grouped by characteristic. Examples of characteristics include:
正確答案: D
說明:(僅 VCESoft 成員可見)
問題2
Which of the following is not something you should do when performing a Belbin assessment with an Agile team?
正確答案: C
說明:(僅 VCESoft 成員可見)
問題3
Assume that you have calculated the following costs of quality:
Average cost of detection: €350
Average cost of internal failure: €250
Average cost of external failure: €4,500
The average costs of detection and internal failure are calculated using the number of defects found prior to release, while the average cost of external failure is calculated using the number of defects found after release.
What is the saving in cost of quality for each defect found in testing?
Average cost of detection: €350
Average cost of internal failure: €250
Average cost of external failure: €4,500
The average costs of detection and internal failure are calculated using the number of defects found prior to release, while the average cost of external failure is calculated using the number of defects found after release.
What is the saving in cost of quality for each defect found in testing?
正確答案: D
說明:(僅 VCESoft 成員可見)
問題4
You are a tester working in an Agile team in the finance domain. The team consists of 6 members, and you are the only tester. The team is responsible for the development and maintenance of a mobile front-end application. The application is considered to be critical with respect to customer impact and market branding.
You have been asked to identify which test management activity needs to be performed within the team to enhance test maturity and achieve a higher level of product quality.
Which test management activity would you recommend the team should adopt?
You have been asked to identify which test management activity needs to be performed within the team to enhance test maturity and achieve a higher level of product quality.
Which test management activity would you recommend the team should adopt?
正確答案: B
說明:(僅 VCESoft 成員可見)
問題5
Which of the following factors influences the risk impact?
正確答案: B
說明:(僅 VCESoft 成員可見)
問題6
Which of the following characteristics of risk-based techniques is not appropriate to a more heavyweight risk- based technique?
正確答案: D
說明:(僅 VCESoft 成員可見)