問題1
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

正確答案: B
說明:(僅 VCESoft 成員可見)
問題2
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

正確答案: B
說明:(僅 VCESoft 成員可見)
問題3
What is the result of a forward pass calculation?

正確答案: B
說明:(僅 VCESoft 成員可見)
問題4
Time-scaled logic diagrams are

正確答案: B
說明:(僅 VCESoft 成員可見)
問題5
An early start constraint dictates

正確答案: B
說明:(僅 VCESoft 成員可見)
問題6
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

正確答案: C
說明:(僅 VCESoft 成員可見)
問題7
When resource leveling craft labor for a critical path schedule, the scheduler

正確答案: D
說明:(僅 VCESoft 成員可見)
問題8
The BEST reason to use multiple calendars is to:

正確答案: A
說明:(僅 VCESoft 成員可見)
問題9
Determine the correct formula and date for the late start for the Activity 11001:

正確答案: C
說明:(僅 VCESoft 成員可見)
問題10
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

正確答案: A
說明:(僅 VCESoft 成員可見)
問題11
Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

正確答案: A
說明:(僅 VCESoft 成員可見)
問題12
During the Bid Phase, do the planning and scheduling project documents impact the Bid pricing?

正確答案: A
問題13
When are KPIs defined?

正確答案: A
問題14
Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor has included several reports with its submittal, including a report that sorts all activities by total float. What is the value of this report?

正確答案: C
問題15
In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

正確答案: B
說明:(僅 VCESoft 成員可見)