問題1
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
正確答案: A
說明:(僅 VCESoft 成員可見)
問題2
What are two differences between a notice and other communications under the FIDIC Red Book (edition
2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
正確答案: A,B
說明:(僅 VCESoft 成員可見)
問題3
Which of the following documents form part of a FIDIC Construction Contract [ " Red Book " (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
正確答案: D,E
說明:(僅 VCESoft 成員可見)
問題4
(Under the FIDIC Yellow Book (edition 1999), any delay caused by Authorities will be considered as a cause of Delay under sub paragraph (b) of Sub-Clause 8.5 under the only condition that the Contractor has diligently followed the procedures laid down by the public authorities in the Country. Is this statement true or false?)
正確答案: B
說明:(僅 VCESoft 成員可見)
問題5
You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?
正確答案: C
說明:(僅 VCESoft 成員可見)
問題6
In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom?
(1 correct response applies)
(1 correct response applies)
正確答案: D
說明:(僅 VCESoft 成員可見)
問題7
(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
Choose all of the correct answers (multiple possibilities).)
正確答案: C,D
說明:(僅 VCESoft 成員可見)
問題8
(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)
正確答案: B
說明:(僅 VCESoft 成員可見)
問題9
In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an " ad-hoc " basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)
正確答案: A
說明:(僅 VCESoft 成員可見)