問題1
What could be a consequence of the confirmation of an operation?

正確答案: C
問題2
Which of the following items of master data are needed for repetitive manufacturing? (Choose three)

正確答案: A,D,E
問題3
What master data do you need for material replenishment using the KANBAN procedure? (Choose two)

正確答案: B,C
問題4
What does SAP ERP mean?

正確答案: D
問題5
Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)

正確答案: B,D,E
問題6
Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?

正確答案: A
問題7
An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?

正確答案: C
問題8
You want to use the function "Read PP master data" in the production order. However, while calling the function you receive an error message.
What could be the reason?

正確答案: B